The most common erection estimating mistake is treating the crane like labor: divide the field hours by the crew and call that the schedule. The crane doesn't work that way. Its day is spent in a cycle whose length barely cares what's on the hook.
Why tonnage is the wrong driver
Watch a raising gang for an hour and count what actually takes time: hook on, lift, swing, land, hang two bolts per end (the OSHA minimum before release), unhook, swing back. Almost none of that cycle changes whether the piece is a W12X26 or a W21X62. A heavy job and a light job with the same piece count erect in roughly the same number of crane days; the heavy job just moves more tons in them.
That's why published erection rates are quoted in pieces. Working figures from public sources cluster tightly:
| Source basis | Rate |
|---|---|
| Low-rise, good access (8-hr day) | ~24 picks/day, falling to ~21 on tall lifts |
| Tower crane, typical | ~20 picks/day |
| Hook-time case study | 39 measured, 60 at peak |
| Common planning target | 15 – 25 picks per crew per day |
A planning number in the mid-20s per crane per day is a sound starting point for conventional low-rise work. Complex rigging, tight sites, and field-welded connections pull it down; a repetitive one-story frame with truck access under the hook pulls it up.
The crew doesn't shorten the crane
Here's the part that breaks the labor-style math. The crew working a crane is a raising gang of about five: a foreman, two hooking on at the ground, two connecting up top. That gang is sized to the crane's cycle. Add two more ironworkers and the crane does not go faster; the extra hands stand around, or you've actually started a second gang, and a second gang needs a second crane.
So keep two separate calculations:
- Labor duration scales with crew: field hours ÷ (crew size × hours per day). This prices the ironworkers.
- Crane duration scales with picks: piece count ÷ picks per day. This prices the equipment, and it's crew-independent.
On most jobs the two land close together, because the gang is sized to the crane. When they don't, believe the picks: a 300-piece frame at 25 picks a day is 12 crane days no matter what the labor math says, and quoting 8 days of crane on it is a hole in the bid.
Building the erection number
-
Count the picks from the takeoff
Every shipped piece that flies is a pick: beams, columns, braces, and the misc that goes up on the hook. A takeoff kept by piece gives you this for free; a takeoff kept only in tons doesn't, which is one more reason to keep it by piece.
-
Pick a picks-per-day rate for the site
Start in the low-to-mid 20s per crane. Adjust for height, access, connection type, and how repetitive the frame is. Your own last few jobs beat any published figure.
-
Size and price the crane for the duration
Piece count ÷ rate = crane days. Then price the machine that the heaviest, farthest pick requires, not the average one. A 100-ton crawler runs roughly $3,000 – $5,000 per day; carry mobilization in and out as its own line.
-
Price the labor separately
Field hours ÷ (gang × hours) gives the labor duration, at your field rates. Keep it a separate line from the crane so a change in one doesn't silently reprice the other.
-
Sanity-check against $/ton bands
Once the bottom-up number exists, divide by tonnage and compare against typical erection $/ton ranges. Outliers usually mean a missed mobilization, a wrong rate, or a pick count that included loose material.
Common holes in erection bids
- Equipment buried in a labor rate. When the crane hides inside an hourly composite, nobody notices it's wrong until the job is running.
- One crane priced, two needed. If the schedule requires two gangs, it requires two machines. Check the calendar, not just the hours.
- Small picks ignored. Stairs, rails hung with the hook, and roof frames are picks too. They're light, and they cost the same cycle as a beam.
- Weather and site days. Crane days are calendar days; a rate that assumes zero lost days is an optimistic rate.
Steel Estimator Pro derives crane days from the takeoff
The equipment tab can auto-derive crane duration from the piece count at your picks-per-day rate, priced separately from field labor, so the two never blur into one number.