Galvanizing is priced by the pound. Paint is priced by the square foot. Miss that one difference and the same finish spec gets over-bid on heavy steel and under-bid on light steel, job after job.
Two different units, two different winners
A hot-dip galvanizer weighs the load; the invoice is dollars per hundredweight of steel. A paint line covers surface; whatever the quote says on its face, the cost tracks square footage of prepared, coated steel.
Now look at how members differ. A heavy column carries very little surface per pound. A picket railing is nearly all surface and hardly any pounds. So the ratio of surface area to weight, square feet per ton, decides which coating is expensive on which steel:
| Steel | Surface vs weight | Tendency |
|---|---|---|
| Heavy W shapes, built-up members | Low sqft/ton | Galvanizing costs relatively more, paint relatively less |
| Typical commercial framing | Middle | Either can win; the shop's logistics usually decide |
| Rails, pickets, light angles, grating | High sqft/ton | Paint labor explodes; galvanizing by weight often wins |
This is why a takeoff that tracks surface area per section, not just tonnage, is the difference between pricing a finish and guessing it. The rule of thumb fails exactly where the money is: on misc metals.
What galvanizing quotes hide
- Trucking both ways. The kettle is at the galvanizer's plant, not yours. Freight to and from is real money and real schedule.
- Venting and drainage. Hollow sections need vent and drain holes before dipping. That's shop labor, and on HSS-heavy jobs it adds up.
- Kettle limits and double dipping. Pieces longer than the kettle get double-dipped at a premium, or redesigned. Check the longest member early.
- Touch-up and field repairs. Welded field connections get cold-galv repair. Small line, but it belongs in the bid.
- Minimum lot charges. A handful of small pieces can cost the minimum, not the per-pound rate.
What paint quotes hide
- Surface prep is the cost. The spec's blast standard drives more of the price than the coating itself. An SSPC-SP6 blast and a wire-brush clean are different bids.
- System, not coat. A primer-only shop coat and a three-coat high-performance system differ by several times, per square foot, in both material and handling.
- Handling between coats. Every coat means moving, racking, drying, and touching the piece again. Multi-coat systems on big weldments eat crane and floor time.
- Overspray reality. Complex shapes with lattice or perforations use far more paint than their net area suggests.
How to bid it cleanly
-
Carry surface area in the takeoff
Every structural section has a known surface area per foot; carry it on the row, alongside weight. Then both coating models price from the same takeoff without a second measuring pass.
-
Price the spec, not the word
"Galvanized" and "painted" aren't prices. Get the blast standard, the system, and the mil thickness out of the spec section before putting a number to it.
-
Split the misc from the structural
Coating a rail package and coating a frame are different problems. Price them separately, with the misc priced from its real (high) surface area.
-
Carry the side costs as lines
Freight to the galvanizer, vent and drain, touch-up, masking of faying surfaces: name them in the estimate so scope review can see them, instead of padding a rate and hoping.
Coating markets move with zinc prices, fuel, and local competition; get current quotes from your galvanizer and coater rather than relying on any published rate. The structural point here is the unit mismatch, and that doesn't change.